Pipeline Projects

Pipeline Projects

Northwood Avenue

Investment in Your Community: $4 Million

Project Start Date: January 2012

Project End Date: Spring 2013

Pipeline Replaced: More than 44,000 feet 

Customers Impacted: Approximately 1,480 customers 

Work will be done on these streets:

  • E. 16th, 17th,& 18th Avenue
  • E. 19th & 20th Avenue
  • Norwich Avenue
  • Northwood Avenue
  • Summit Street
  • Indianola Avenue
  • Luka Avenue
  • Waldeck Avenue
  • Fourth Street
  • Lane Avenue
  • Tuller Street
  • N. High Street
  • Woodruff Avenue
  • Pearl Street
  • Neil Avenue
  • Frambes Avenue